Date of exemption
05/08/2021
Service or team
Environment and operations
Description
Surfacing of the footpaths sometimes requires two coats rather than one coat. This can only be known after the first course has been laid. The contract with Idverde was to resurface with one coat only. Another coat is needed.
Reason for exemption
They are familiar with site, its constraints, the specification, and the quality standards expected as they have already worked on this before. Competitive rates used, using spons external works and landscaping pricing guide, 4 weeks timeframe on this piece of work.
Total value
£34,892
Approve by
Head of Finance